Electricity sector in Peru
Encyclopedia
The electricity sector in Peru
has experienced impressive improvements in the past 15 years. Access to electricity has increased from 45% in 1990 to 88.8% in July 2011, while service quality and efficiency of service provision improved. These improvements were made possible through privatization
s following reforms initiated in 1992. At the same time, electricity tariff
s have remained in line with the average for Latin America
.
However, several challenges remain. Chief among them are the still very low level of access in rural areas and the untapped potential of some renewable energies, in particular wind
and solar energy, due to an inadequate regulatory framework.
The current electricity generation capacity is evenly divided between thermal and hydroelectric sources. A renewed recent dynamism of the electricity sector in the country is based on the shift to natural gas plants, which will be mainly fed from the production of the Camisea gas field
in the Amazon Rainforest
.
The National Interconnected System (SEIN) serves 85% of the connected population, with several “isolated” systems covering the rest of the country. While investment in generation, transmission and distribution in urban areas is predominantly private, resources for rural electrification come solely from public sources.
. In 2006, the country had 6.7 GW of installed capacity, 52% being thermal and 48% hydroelectric, with a negligible share of other renewable sources. Of the total capacity, 84% (5.63 GW) enters the electricity market, while the remaining 16% (1,03 GW) is generated for self-consumption.
However, electricity generation is not evenly divided between the two dominating sources. In 2006, 72% of Peru’s total electricity generation came from hydroelectric plants (total generation was 27.4 TWh), with conventional thermal plants only in operation during peak load periods or when hydroelectric output is curtailed by weather events. This “underuse” of the country’s thermal capacity is due to the high variable costs of thermal generation. In 2004, the country’s reserve margin was estimated at 45%. However, when those high cost thermal plants were taken out of the equation, margins fell to as low as 15%.
In an attempt to reduce the country’s reliance upon hydroelectricity, the Peruvian government has encouraged greater investment in gas-fired power plants. The controversial Camisea Gas Project
has opened up natural gas production in Peru, with the first new 140 MW gas-fired power plant in Tumbas to start operations by the end of 2007. The Camisea project is considered strategic for it is expected to contribute to reduce the existing deficit in Peru’s hydrocarbons trade balance by substituting imports (mainly of diesel and LPG) and allowing exports (naphta, LPG surpluses).
The dynamic nature of the electricity sector has continued during 2007, with an estimated 9.3% increase in generation, which is expected to reach 30 TWh. This increase is mainly due to the existing positive conditions for thermal generation through the use of natural gas in new plants and also to an increase in hydroelectric generation due to the availability of hydrological resources in the existing hydroelectric facilities.
To meet this increasing demand, Peru will rely on natural gas, which is the most cost competitive option among all other fuel types. As such, it is expected that installed capacity of gas-fired electricity generation increases from 0.3 GW in 2002 to 6.0 GW in 2030. It is expected that, from 2026 onwards, natural gas will acquire the dominant share in the electricity generation mix, reaching 44% in 2030 compared with hydroelectricity's 37% share for the same year.
region Peru has one of the lowest rural electrification rates in Latin America. Coverage in the predominantly poor rural areas is about 30%, with more than six million people without access to electricity. In its 2004 National Rural Electrification Plan (PNER), the Government of Peru reiterated its commitment to reduce the electrification gap, aiming to increase rural coverage from 30% to 75% by 2013.
of 13 interruptions and 14 hours for the LAC
region.
average. Transmission losses for the same year have been estimated at 4.7%.
The Energy and Mining Investment Supervisory Body (OSINERGMIN - Organismo Supervisor de Inversión en Energía y Miniería), created in 1996 as OSINERG (Mining competences were added recently, in January 2007), is in charge of enforcing compliance with the Electricity Concessions Law (LCE) of 1992 and is also in charge of ensuring the electricity public service. OSINERG is as well the body responsible for enforcing the fiscal obligations of the license holders as established by the law and its regulation. Finally, it is responsible for monitoring compliance of the System Economic Operation Committees (COES) functions and for determining biannually the percentages of market participation by the companies.
In 2000, OSINERG was merged with the Electricity Tariffs Commission (CTE), currently known as Adjunct Office for Tariff Regulation (GART). Together, they are in charge of fixing generation, transmission and distribution tariffs and the tariff adjustment conditions for the end consumers. They also determine the tariffs for transport and distribution of gas by pipeline.
As for rural electrification, the National Rural Electrification Office (DGER) is in charge of the National Rural Electrification Plan (PNER), which is framed under the policy guidelines set by the Ministry of Energy and Mines. DGER is in charge of the execution and coordination of projects in rural areas and regions of extreme poverty.
Finally, the National Institute for Defense of Competition and the Protection of Intellectual Property (INDECOPI) is in charge of monitoring compliance with the Anti-monopoly
and Anti-oligopoly
Law of 1997.
ELP dominates hydroelectric production, with 32% of the total, while EDEGEL leads thermal generation also with 32% of the total.
Private companies dominate the generation sector. In terms of participation, state companies hold 31% of generation capacity, with the remaining 69% in private hands. Production percentages are 40% and 60% for the public and private companies respectively.
Public distribution companies supply electricity to 55% of the existing clients, with the remaining 45% in hands of the private utilities. However, in terms of electricity distributed, private companies have the lead with 71% of the total as opposed to 29% for the public ones.
is the only renewable resource exploited in Peru. In 2006, it accounted for 48% of total installed capacity and 72% of electricity generated. The largest hydroelectric facility in the country is the 900 MW Mantaro
Complex in southern Peru, which is operated by state-owned Electroperu. The two hydroelectric plants at the complex generate over one-third of Peru’s total electricity supply. In February 2006, Egecen S.A. completed construction of the 130-MW, Yuncán hydroelectric plant, located northeast of Lima. The plant will be operated by EnerSur, a subsidiary of Brussels-based Suez Energy International.
Construction on the multi-purpose Olmos Transandino Project has been underway since 2006 and in February 2010, the contract for its hydroelectricity
power plant is expected to be issued. The power station
in northwest Peru's Cajamarca
province will have a 600 MW capacity and produce 4,000 GWh annually.
to the energy matrix in Peru is negligible, with just 0.7 MW of installed capacity in 2006.
Studies from the National Meteorological and Hydrological Service (SENAMHI) have estimated a total windpower potential of 19 GWh/year for Peru, or about 70% of current electricity consumption. The Departments of Talara
, Laguna Grande, Marcona and Pta. Atico are the regions with the largest wind potential. However, the absence of a regulatory framework and of a reliable record of wind potential, together with the lack of human, financial, and technical resources, has so far hindered the exploitation of Peru’s windpower potential.
The structural reform process that started in 1992 under the government of President Alberto Fujimori
led to the privatization of the electricity sector in a decade in which most of the countries in the region underwent a similar process. The restructuring process, articulated in the Electricity Concessions Law (LCE) of 1992, unbundled the vertically integrated state monopoly into generation
, transmission and distribution
and led the basis for the introduction of private operators and competition for generation and commercialization, with transmission and distribution regulated on the basis of free entry and open access. The 1992 Law was modified by Law No. 26876 (Anti-monopoly and Anti-oligopoly Law) in 1997. The process of concessions and transfer of generation assets to private companies was started in 1994 and relaunched in 2002 as it had not been completed yet.
Private companies emerging from the 1992 reforms made substantial investment commitments that were fulfilled in the following years. Investment figures reached their highest levels in the period 1996-1999, declining afterwards once the commitments had been fulfilled. The high level of investment led to annual average increases in installed capacity of 9.2%, a rate that was not matched by the increase in demand, which increased at only 4.7% per year on average. As a result, the level of reserves in the National Interconnected System (SEIN) increased at average rates of 23.2%. Investments in transmission and distribution led to increases in coverage from 53% in 1993 to 76% in 2004.
.
As for rural electrification, there have been several attempts to change the existing institutional and legal framework. In recent years, there have been two laws passed by Congress (the Law for Electrification of Rural and Isolated or Frontier Areas in 2002 and the Law to Regulate the Promotion of Private Investment in Rural Electrification in 2004) but neither of them has been implemented due to conflicts with provisions in other laws.
weighted average
in 2005 was US$0.115.
In the unregulated market, the average tariff for final customers was US$0.0558 per kWh for the electricity supplied directly from the generators and US$0.0551 per kWh for the electricity supplied by distribution companies.
The number of households that benefit from this scheme is over 2.4 million (out of the 3.6 million connected households at the national level). In July 2004, the FOSE was extended to cover up to 50% of the bill in the National Interconnected System (SEIN) and 62.5% in the isolated systems for the users with consumption below 30kWh, including as well a special focus by geographic location (rural-urban).
(See Evaluation of the FOSE for a detailed analysis of the results of the FOSE.)
Total investment in the electricity sector in 2006 was US$ 480.2 million, which was 22% higher than the amount for 2005. Investment in generation
, transmission and distribution
added up to US$446.2 million, while investment by the Executive Office for Projects (DEP) in the Rural Electrification was US$34 million. The table below summarizes the contribution of both the private and the public sector :
Source: Ministerio de Energia y Minas 2007
(See Dirección Ejecutiva de Proyectos Solar PV Rural Electrification Project)
Investment by private companies has taken off after having reached very low numbers by 2003 (US$120 million, matching public investment for that year) after the general decline in investment that happened from 1999 onwards.
To expand coverage, the Government of Peru has been spending an average of US$40–50 million per year in the last ten years for electrification. These investments were carried out through social funds (e.g. FONCODES – Cooperation Fund for Social Development) and, to a larger extent, by the Executive Office for Projects (DEP), a division of the Ministry of Energy and Mines (MEM). The DEP, which is currently in the process of being absorbed by the National Rural Electrification Office (DGER), is in charge of planning, designing and constructing the rural electricity systems. Once they are finalized, the rural electricity systems are handed over for operation either to state-owned distribution companies or to a specially created state-owned asset-holding company that manages the systems under operation contracts with state-owned companies, or municipalities.
As for transmission, 100% is in the hands of several private companies, while 71% of electricity distributed and 45% of the existing clients were also controlled by private companies.
Peru
Peru , officially the Republic of Peru , is a country in western South America. It is bordered on the north by Ecuador and Colombia, on the east by Brazil, on the southeast by Bolivia, on the south by Chile, and on the west by the Pacific Ocean....
has experienced impressive improvements in the past 15 years. Access to electricity has increased from 45% in 1990 to 88.8% in July 2011, while service quality and efficiency of service provision improved. These improvements were made possible through privatization
Privatization
Privatization is the incidence or process of transferring ownership of a business, enterprise, agency or public service from the public sector to the private sector or to private non-profit organizations...
s following reforms initiated in 1992. At the same time, electricity tariff
Tariff
A tariff may be either tax on imports or exports , or a list or schedule of prices for such things as rail service, bus routes, and electrical usage ....
s have remained in line with the average for Latin America
Latin America
Latin America is a region of the Americas where Romance languages – particularly Spanish and Portuguese, and variably French – are primarily spoken. Latin America has an area of approximately 21,069,500 km² , almost 3.9% of the Earth's surface or 14.1% of its land surface area...
.
However, several challenges remain. Chief among them are the still very low level of access in rural areas and the untapped potential of some renewable energies, in particular wind
Wind power
Wind power is the conversion of wind energy into a useful form of energy, such as using wind turbines to make electricity, windmills for mechanical power, windpumps for water pumping or drainage, or sails to propel ships....
and solar energy, due to an inadequate regulatory framework.
The current electricity generation capacity is evenly divided between thermal and hydroelectric sources. A renewed recent dynamism of the electricity sector in the country is based on the shift to natural gas plants, which will be mainly fed from the production of the Camisea gas field
Camisea Gas Project
The Camisea Gas Project extracts and transports natural gas originating near the Urubamba River in central Peru, the San Martín Reservoir.-History:...
in the Amazon Rainforest
Amazon Rainforest
The Amazon Rainforest , also known in English as Amazonia or the Amazon Jungle, is a moist broadleaf forest that covers most of the Amazon Basin of South America...
.
The National Interconnected System (SEIN) serves 85% of the connected population, with several “isolated” systems covering the rest of the country. While investment in generation, transmission and distribution in urban areas is predominantly private, resources for rural electrification come solely from public sources.
Installed capacity
Installed generating capacity Peru is evenly divided between thermal and hydroelectric sourcesHydroelectricity
Hydroelectricity is the term referring to electricity generated by hydropower; the production of electrical power through the use of the gravitational force of falling or flowing water. It is the most widely used form of renewable energy...
. In 2006, the country had 6.7 GW of installed capacity, 52% being thermal and 48% hydroelectric, with a negligible share of other renewable sources. Of the total capacity, 84% (5.63 GW) enters the electricity market, while the remaining 16% (1,03 GW) is generated for self-consumption.
However, electricity generation is not evenly divided between the two dominating sources. In 2006, 72% of Peru’s total electricity generation came from hydroelectric plants (total generation was 27.4 TWh), with conventional thermal plants only in operation during peak load periods or when hydroelectric output is curtailed by weather events. This “underuse” of the country’s thermal capacity is due to the high variable costs of thermal generation. In 2004, the country’s reserve margin was estimated at 45%. However, when those high cost thermal plants were taken out of the equation, margins fell to as low as 15%.
In an attempt to reduce the country’s reliance upon hydroelectricity, the Peruvian government has encouraged greater investment in gas-fired power plants. The controversial Camisea Gas Project
Camisea Gas Project
The Camisea Gas Project extracts and transports natural gas originating near the Urubamba River in central Peru, the San Martín Reservoir.-History:...
has opened up natural gas production in Peru, with the first new 140 MW gas-fired power plant in Tumbas to start operations by the end of 2007. The Camisea project is considered strategic for it is expected to contribute to reduce the existing deficit in Peru’s hydrocarbons trade balance by substituting imports (mainly of diesel and LPG) and allowing exports (naphta, LPG surpluses).
The dynamic nature of the electricity sector has continued during 2007, with an estimated 9.3% increase in generation, which is expected to reach 30 TWh. This increase is mainly due to the existing positive conditions for thermal generation through the use of natural gas in new plants and also to an increase in hydroelectric generation due to the availability of hydrological resources in the existing hydroelectric facilities.
Demand
In 2006, total electricity consumption in Peru was 24 TWh, which corresponds to 872 kWh per capita per year. The consumption share for the different economic sectors is as follows :- Industrial: 66%
- Residential: 24%
- Commercial: 19%
- Public lighting: 3%
Demand and supply projections
In terms of demand projections, the Ministry of Energy and Mines estimates that electricity demand will increase between 5.6% and 7.4% per year between 2007-2015. It is expected that per capita electricity demand will reach 1,632 kWh in 2030.To meet this increasing demand, Peru will rely on natural gas, which is the most cost competitive option among all other fuel types. As such, it is expected that installed capacity of gas-fired electricity generation increases from 0.3 GW in 2002 to 6.0 GW in 2030. It is expected that, from 2026 onwards, natural gas will acquire the dominant share in the electricity generation mix, reaching 44% in 2030 compared with hydroelectricity's 37% share for the same year.
Access to electricity
In 2006, 79% of the population in Peru had access to electricity, a percentage that is below the 94.6 average for the LACLAC
-Places:* Los Angeles County in California* La Crescenta, California, unincorporated area in Los Angeles County* California State Prison, Los Angeles County...
region Peru has one of the lowest rural electrification rates in Latin America. Coverage in the predominantly poor rural areas is about 30%, with more than six million people without access to electricity. In its 2004 National Rural Electrification Plan (PNER), the Government of Peru reiterated its commitment to reduce the electrification gap, aiming to increase rural coverage from 30% to 75% by 2013.
Interruption frequency and duration
In 2005, the average number of interruptions per subscriber was 14.5, while duration of interruptions per subscriber was 18.3 hours. Both numbers are very close to the weighted averagesWeighted mean
The weighted mean is similar to an arithmetic mean , where instead of each of the data points contributing equally to the final average, some data points contribute more than others...
of 13 interruptions and 14 hours for the LAC
LAC
-Places:* Los Angeles County in California* La Crescenta, California, unincorporated area in Los Angeles County* California State Prison, Los Angeles County...
region.
Distribution and transmission losses
Losses in 2006 amounted to 11% of total production. Distribution losses were 6.3%, down from 22 % a decade before and below the 13.5% LACLAC
-Places:* Los Angeles County in California* La Crescenta, California, unincorporated area in Los Angeles County* California State Prison, Los Angeles County...
average. Transmission losses for the same year have been estimated at 4.7%.
Policy and regulation
The National Electricity Office (DGE - Dirección General de la Electricidad), under the Ministry of Energy and Mines (MEM), is in charge of setting electricity policies and regulations and of granting concessions. It is also responsible for elaborating generation and transmission expansion plans and has to approve the relevant procedures for the operation of the electricity system.The Energy and Mining Investment Supervisory Body (OSINERGMIN - Organismo Supervisor de Inversión en Energía y Miniería), created in 1996 as OSINERG (Mining competences were added recently, in January 2007), is in charge of enforcing compliance with the Electricity Concessions Law (LCE) of 1992 and is also in charge of ensuring the electricity public service. OSINERG is as well the body responsible for enforcing the fiscal obligations of the license holders as established by the law and its regulation. Finally, it is responsible for monitoring compliance of the System Economic Operation Committees (COES) functions and for determining biannually the percentages of market participation by the companies.
In 2000, OSINERG was merged with the Electricity Tariffs Commission (CTE), currently known as Adjunct Office for Tariff Regulation (GART). Together, they are in charge of fixing generation, transmission and distribution tariffs and the tariff adjustment conditions for the end consumers. They also determine the tariffs for transport and distribution of gas by pipeline.
As for rural electrification, the National Rural Electrification Office (DGER) is in charge of the National Rural Electrification Plan (PNER), which is framed under the policy guidelines set by the Ministry of Energy and Mines. DGER is in charge of the execution and coordination of projects in rural areas and regions of extreme poverty.
Finally, the National Institute for Defense of Competition and the Protection of Intellectual Property (INDECOPI) is in charge of monitoring compliance with the Anti-monopoly
Monopoly
A monopoly exists when a specific person or enterprise is the only supplier of a particular commodity...
and Anti-oligopoly
Oligopoly
An oligopoly is a market form in which a market or industry is dominated by a small number of sellers . The word is derived, by analogy with "monopoly", from the Greek ὀλίγοι "few" + πόλειν "to sell". Because there are few sellers, each oligopolist is likely to be aware of the actions of the others...
Law of 1997.
Generation
In 2006, 38 companies generated electricity for the market, while 78 companies produced electricity for their own use. Among the 38 companies supplying energy to the market, four of them accounted for 70% of the total capacity :- EDEGEL S.A.A.: 1,574MW
- Electroperú S.A. (ELP): 1,032 MW
- Energía del Sur S.A. (ENERSUR): 725 MW
- EGENOR: 522 MW
ELP dominates hydroelectric production, with 32% of the total, while EDEGEL leads thermal generation also with 32% of the total.
Private companies dominate the generation sector. In terms of participation, state companies hold 31% of generation capacity, with the remaining 69% in private hands. Production percentages are 40% and 60% for the public and private companies respectively.
Transmission
In Peru, 100% of the transmission activities are in private hands. In 2006, there were 6 purely transmission companies that participated in electricity transmission in Perú: Red de Energía del Perú S.A. (REPSA), with 28% of the transmission lines; and Consorcio Energético Huancavelica (CONENHUA), Consorcio Transmantaro S.A. (S.A. Transmantaro), Eteselva S.R.L, Interconexión Eléctrica ISA Perú (ISAPERU) and Red Eléctrica del Sur.S.A. (REDESUR), with 15% of the lines. Generation and distribution utilities and the companies that generate electricity for their own consumption operate the remaining 57% of the transmission lines.Distribution
In 2006, 63% of the electricity was commercialized by 22 distribution companies , while the remaining 37% was commercialized directly by generation companies. The companies that stood out for their sales to end-consumers were: Luz del Sur (21%), Edelnor (21%), Enersur (9%), Edegel (8%), Electroperú (5%), Hidrandina (4%), Termoselva (4%) and Electroandes (4%).Public distribution companies supply electricity to 55% of the existing clients, with the remaining 45% in hands of the private utilities. However, in terms of electricity distributed, private companies have the lead with 71% of the total as opposed to 29% for the public ones.
Renewable energy resources
The National Environment Fund (FONAM) was created in 1997 and received the mandate from the Peruvian Congress to identify and promote projects that exploit renewable energy sources, introduce clean technologies, and promote energy efficiency and the substitution of highly polluting fuels. However, the contribution of renewable energy sources other than hydroelectricity is still very limited in Peru.Hydroelectricity
HydroelectricityHydroelectricity
Hydroelectricity is the term referring to electricity generated by hydropower; the production of electrical power through the use of the gravitational force of falling or flowing water. It is the most widely used form of renewable energy...
is the only renewable resource exploited in Peru. In 2006, it accounted for 48% of total installed capacity and 72% of electricity generated. The largest hydroelectric facility in the country is the 900 MW Mantaro
Mantaro Valley
The Mantaro Valley, with its main city of Huancayo, lies east of the capital of Peru, Lima. It is a fertile valley containing fields of corn, artichokes, carrots and potatoes, alongside which flows the Mantaro River. The Mantaro Valley is also renowned as an area containing many sites of...
Complex in southern Peru, which is operated by state-owned Electroperu. The two hydroelectric plants at the complex generate over one-third of Peru’s total electricity supply. In February 2006, Egecen S.A. completed construction of the 130-MW, Yuncán hydroelectric plant, located northeast of Lima. The plant will be operated by EnerSur, a subsidiary of Brussels-based Suez Energy International.
Construction on the multi-purpose Olmos Transandino Project has been underway since 2006 and in February 2010, the contract for its hydroelectricity
Hydroelectricity
Hydroelectricity is the term referring to electricity generated by hydropower; the production of electrical power through the use of the gravitational force of falling or flowing water. It is the most widely used form of renewable energy...
power plant is expected to be issued. The power station
Power station
A power station is an industrial facility for the generation of electric energy....
in northwest Peru's Cajamarca
Cajamarca
Cajamarca may refer to:Colombia*Cajamarca, Tolima a town and municipality in Tolima DepartmentPeru* Cajamarca, city in Peru.* Cajamarca District, district in the Cajamarca province.* Cajamarca Province, province in the Cajamarca region....
province will have a 600 MW capacity and produce 4,000 GWh annually.
Wind
The contribution of wind powerWind power
Wind power is the conversion of wind energy into a useful form of energy, such as using wind turbines to make electricity, windmills for mechanical power, windpumps for water pumping or drainage, or sails to propel ships....
to the energy matrix in Peru is negligible, with just 0.7 MW of installed capacity in 2006.
Studies from the National Meteorological and Hydrological Service (SENAMHI) have estimated a total windpower potential of 19 GWh/year for Peru, or about 70% of current electricity consumption. The Departments of Talara
Talara Province
Talara is a province in the Piura Region, Peru. It is bordered by the Pacific Ocean on the west, the Paita Province on the south, the Sullana Province on the east and the Tumbes Region's Contralmirante Villar Province on the north. Its capital is the major port city of Talara...
, Laguna Grande, Marcona and Pta. Atico are the regions with the largest wind potential. However, the absence of a regulatory framework and of a reliable record of wind potential, together with the lack of human, financial, and technical resources, has so far hindered the exploitation of Peru’s windpower potential.
Solar
It has been estimated that Peru has favorable conditions for the development of solar energy projects. However, the country’s solar potential has not been exploited yet. In the mountain ranges located in the South, solar energy reaches average levels above 6 kWh/m2/day, which are among the highest worldwide.Early history
From its inception, the Peruvian electricity system started to be developed by private initiative. In 1955, Law No. 12378 regulated the mechanisms of private participation, establishing a system of concessions with commitments to increase generation capacity by 10% annually. The National Tariff Commission and other mechanisms aiming at guaranteeing the profitability of the investments were then created. However, at the beginning of the 1970s, profound changes took place. In 1972, the de facto military government nationalized the electricity industry through Law No.19521, creating ELECTROPERU (Peru Electricity Company). ELECTROPERU became the owner of all the generation, transmission and distribution assets and came to be in charge of service provision and investment planning. Until the beginning of the 1980s there were large investments in hydroelectric and thermal projects. However, this dynamism started to fade during the 1980s mainly due to the debt crisis that started in 1982 and that precluded new financing in the region. By the beginning of the 1990s, the electricity sector in Peru showed an important deterioration due to low investment in infrastructure, the fact that tariffs did not cover production costs, the restricted investment in maintenance and the systematic destruction of infrastructures by terrorist activities. The results of this crisis were severe: in 1990 only 45% of the population had access to electricity, supply only covered 74% of the demand and distribution losses were above 20%.The structural reform process that started in 1992 under the government of President Alberto Fujimori
Alberto Fujimori
Alberto Fujimori Fujimori served as President of Peru from 28 July 1990 to 17 November 2000. A controversial figure, Fujimori has been credited with the creation of Fujimorism, uprooting terrorism in Peru and restoring its macroeconomic stability, though his methods have drawn charges of...
led to the privatization of the electricity sector in a decade in which most of the countries in the region underwent a similar process. The restructuring process, articulated in the Electricity Concessions Law (LCE) of 1992, unbundled the vertically integrated state monopoly into generation
Electricity generation
Electricity generation is the process of generating electric energy from other forms of energy.The fundamental principles of electricity generation were discovered during the 1820s and early 1830s by the British scientist Michael Faraday...
, transmission and distribution
Electricity distribution
File:Electricity grid simple- North America.svg|thumb|380px|right|Simplified diagram of AC electricity distribution from generation stations to consumers...
and led the basis for the introduction of private operators and competition for generation and commercialization, with transmission and distribution regulated on the basis of free entry and open access. The 1992 Law was modified by Law No. 26876 (Anti-monopoly and Anti-oligopoly Law) in 1997. The process of concessions and transfer of generation assets to private companies was started in 1994 and relaunched in 2002 as it had not been completed yet.
Private companies emerging from the 1992 reforms made substantial investment commitments that were fulfilled in the following years. Investment figures reached their highest levels in the period 1996-1999, declining afterwards once the commitments had been fulfilled. The high level of investment led to annual average increases in installed capacity of 9.2%, a rate that was not matched by the increase in demand, which increased at only 4.7% per year on average. As a result, the level of reserves in the National Interconnected System (SEIN) increased at average rates of 23.2%. Investments in transmission and distribution led to increases in coverage from 53% in 1993 to 76% in 2004.
2000s developments
In September 2000, the Law for the Promotion of Energy Efficiency (Law No. 27345) was approved, declaring support for the efficient use of energy to be in the national interest. The regulation for this Law was approved in October 2007 (by Supreme Decree No. 053-2007-EM). The objectives of the Law are to contribute to energy security, improve the country’s competitiveness, generate surplus for exports, reduce environmental impacts, protect consumers and raise awareness about the importance of efficient energy useEfficient energy use
Efficient energy use, sometimes simply called energy efficiency, is the goal of efforts to reduce the amount of energy required to provide products and services. For example, insulating a home allows a building to use less heating and cooling energy to achieve and maintain a comfortable temperature...
.
As for rural electrification, there have been several attempts to change the existing institutional and legal framework. In recent years, there have been two laws passed by Congress (the Law for Electrification of Rural and Isolated or Frontier Areas in 2002 and the Law to Regulate the Promotion of Private Investment in Rural Electrification in 2004) but neither of them has been implemented due to conflicts with provisions in other laws.
Tariffs
In 2006, the average residential tariff in Peru was US$0.1046 per kWh, LACLAC
-Places:* Los Angeles County in California* La Crescenta, California, unincorporated area in Los Angeles County* California State Prison, Los Angeles County...
weighted average
Weighted mean
The weighted mean is similar to an arithmetic mean , where instead of each of the data points contributing equally to the final average, some data points contribute more than others...
in 2005 was US$0.115.
In the unregulated market, the average tariff for final customers was US$0.0558 per kWh for the electricity supplied directly from the generators and US$0.0551 per kWh for the electricity supplied by distribution companies.
Subsidies
Law No. 275010 created, in November 2001, the Electricity Social Compensation Fund (FOSE). This Fund established a cross-subsidy system among consumers that benefits users with monthly consumption below 100kWh through fixed and proportional discounts. The fixed discount applies to consumers between 30 and 100 kWh and the proportional discount is targeted to those with consumptions below 30 kWh. The amount of the discounts is financed through a surcharge in the tariff paid by the regulated consumers with monthly consumptions above 100 kWh.The number of households that benefit from this scheme is over 2.4 million (out of the 3.6 million connected households at the national level). In July 2004, the FOSE was extended to cover up to 50% of the bill in the National Interconnected System (SEIN) and 62.5% in the isolated systems for the users with consumption below 30kWh, including as well a special focus by geographic location (rural-urban).
(See Evaluation of the FOSE for a detailed analysis of the results of the FOSE.)
Investment by subsector
In 2004, annual investment needs in the electricity sector up to 2016 were estimated at US$200 million, considering a projected annual demand increase of 5%.Total investment in the electricity sector in 2006 was US$ 480.2 million, which was 22% higher than the amount for 2005. Investment in generation
Electricity generation
Electricity generation is the process of generating electric energy from other forms of energy.The fundamental principles of electricity generation were discovered during the 1820s and early 1830s by the British scientist Michael Faraday...
, transmission and distribution
Electricity distribution
File:Electricity grid simple- North America.svg|thumb|380px|right|Simplified diagram of AC electricity distribution from generation stations to consumers...
added up to US$446.2 million, while investment by the Executive Office for Projects (DEP) in the Rural Electrification was US$34 million. The table below summarizes the contribution of both the private and the public sector :
Subsector | Private companies | Public companies | Total | |
---|---|---|---|---|
Generation | million US$ | 260.4 | 29.2 | 289.6 |
% participation | 90% | 10% | ||
Transmission | million US$ | 16.5 | 16.5 | |
% participation | 100% | 0% | ||
Distribution | million US$ | 73.5 | 66.5 | 140.1 |
% participation | 52% | 48% | ||
Total | million US$ | 350.5 | 95.7 | 446.2 |
Source: Ministerio de Energia y Minas 2007
(See Dirección Ejecutiva de Proyectos Solar PV Rural Electrification Project)
Investment by private companies has taken off after having reached very low numbers by 2003 (US$120 million, matching public investment for that year) after the general decline in investment that happened from 1999 onwards.
Investment requirements
To meet expected demand, total investment needs in electricity generation and transmission between 2002 and 2030 are estimated to be US$16.2-20.7 million.Rural electrification
After the power sector reform in the early 1990s, rural electrification in Peru has been limited to direct investment by the central government, without any additional funds from communities, regional governments or service providers. One important issue deterring electricity distribution companies from investing in rural electrification is the fact that they hold concession areas concentrated in small areas around urban centers and are only under the obligation to meet service requests within 100 meters of the existing network.To expand coverage, the Government of Peru has been spending an average of US$40–50 million per year in the last ten years for electrification. These investments were carried out through social funds (e.g. FONCODES – Cooperation Fund for Social Development) and, to a larger extent, by the Executive Office for Projects (DEP), a division of the Ministry of Energy and Mines (MEM). The DEP, which is currently in the process of being absorbed by the National Rural Electrification Office (DGER), is in charge of planning, designing and constructing the rural electricity systems. Once they are finalized, the rural electricity systems are handed over for operation either to state-owned distribution companies or to a specially created state-owned asset-holding company that manages the systems under operation contracts with state-owned companies, or municipalities.
Summary of private participation in the electricity sector
The structural reform process that started in 1992 unbundled the vertically integrated state monopoly and led to the privatization of the electricity sector. Today, private companies dominate the generation sector with almost 70% of capacity in their hands. Although there are about 40 companies that generate electricity for the market, just 4 of them (EDEGEL S.A.A., Electroperú S.A., Energía del Sur S.A. and EGENOR) account for 70% of the total capacity.As for transmission, 100% is in the hands of several private companies, while 71% of electricity distributed and 45% of the existing clients were also controlled by private companies.
PROCLIM) was created to implement the aforementioned Strategy. PROCLIM aims to contribute to poverty reduction by promoting the integration of climate change and air quality issues in sustainable development policies.Greenhouse gas emissionsOLADE (Latin American Energy Association) estimated that CO2 emissions from electricity production in 2003 were 3.32 million tons of CO2, which corresponds to 13% of total emissions from the energy sector.CDM projects in electricityCurrently (November 2007), there are seven registered CDM projects in the electricity sector in Peru, with overall estimated emission reductions of 800,020 tCO2e per year.
Source: UNFCCC The National Environment Fund FONAM is the focal point for CDM projects in Peru. Inter-American Development BankThe Inter-American Development BankInter-American Development Bank The Inter-American Development Bank is the largest source of development financing for Latin America and the Caribbean... is currently providing technical assistance for a Sustainable Energy Services project in Peru. This is a US$850,000 project of which the IDB is contributing US$750,000. World BankCurrently, the World BankWorld Bank The World Bank is an international financial institution that provides loans to developing countries for capital programmes.The World Bank's official goal is the reduction of poverty... is funding a Rural Electrification project in Peru. This is a 6-year (2006-2012), US$145 million project to which the World Bank is contributing US$50 million in lending and the Global Environment Facility (GEF) a US$10 million grant. This project is increasing access to efficient and sustainable electricity services and improving quality of life and income generation opportunities in rural areas. Sources
See also