Production leveling
Encyclopedia
Production leveling, also known as production smoothing or – by its Japanese original term – , is a technique for reducing the muda waste and vital to the development of production efficiency in the Toyota Production System
Toyota Production System
The Toyota Production System is an integrated socio-technical system, developed by Toyota, that comprises its management philosophy and practices. The TPS organizes manufacturing and logistics for the automobile manufacturer, including interaction with suppliers and customers...

 and Lean Manufacturing
Lean manufacturing
Lean manufacturing, lean enterprise, or lean production, often simply, "Lean," is a production practice that considers the expenditure of resources for any goal other than the creation of value for the end customer to be wasteful, and thus a target for elimination...

. The general idea is to produce intermediate goods at a constant rate, to allow further processing to be carried out at a constant and predictable rate.

Ideally production can easily be leveled where demand is constant but in the real world where actual customer demand appears to fluctuate two approaches have been adopted in lean: Demand leveling and production leveling through flexible production.

On a production line, as in any process, fluctuations in performance increase waste. This is because equipment, workers, inventory and all other elements required for production must always be prepared for peak production. This is a cost of flexibility. If a later process varies its withdrawal of parts in terms of timing and quality, the range of these fluctuations will increase as they move up the line towards the earlier processes. This is known as demand amplification.

To prevent fluctuations in production, even in outside affiliates, it is important to try to keep fluctuation in the final assembly line to zero. Toyota's final assembly line never assembles the same automobile model in a batch. Production is leveled by making first one model, then another model, then yet another. In production leveling, batches are made as small as possible in contrast to traditional mass production, where bigger is considered better. When the final assembly process assembles cars in small batches, then the earlier processes, such as the press operation, have to follow the same approach. Long changeover times have meant that economically it was sound to punch out as many parts as possible. In the Toyota Production System this does not apply. Die changes (changeovers) are made quickly (SMED) and improved even more with practice. In the 1940s it took two to three hours, in the 1950s it dropped from one hour to 15 minutes, now it takes three minutes.

Leveling by volume or by product type or mix

Production leveling can refer to leveling by volume, or leveling by product type or mix, although the two are closely related.

Leveling by volume

If for a family of products that use the same production process there is a demand that varies between 800 and 1,200 units then it might seem a good idea to produce the amount ordered. Toyota's view is that production systems that vary in the required output suffer from mura
Mura (Japanese term)
Mura is traditional general Japanese term for unevenness, irregularity or inconsistency in physical matter or human spiritual condition. It is also a key concept in performance improvement systems such as the Toyota Production System. Mura is one of the three types of waste . Waste reduction is an...

 and muri
Muri (Japanese term)
Muri is a Japanese term for overburden, unreasonableness or absurdity, which has become popularized in the West by its use as a key concept in the Toyota Production System.-Avoidance of muri in Toyota manufacturing:...

 with capacity being 'forced' in some periods. So their approach is to manufacture at the long-term average demand and carry an inventory proportional to the variability of demand, stability of the production process and the frequency of shipments. So for our case of 800-1,200 units, if the production process were 100% reliable and the shipments once a week, then the production would be 1,000 with minimum standard inventory of 200 at the start of the week and 1,200 at the point of shipment. The advantage of carrying this inventory is that it can smooth production throughout the plant and therefore reduce process inventories and simplify operations which reduces costs.

Leveling by product

Most value streams produce a mix of products and therefore face a choice of production mix and sequence. It is here that the discussions on economic order quantities take place and have been dominated by changeover times and the inventory this requires. Toyota's approach resulted in a different discussion where it reduced the time and cost of changeovers so that smaller and smaller batches were not prohibitive and lost production time and quality costs were not significant. This meant that the demand for components could be leveled for the upstream sub-processes and therefore lead time and total inventories reduced along the entire value stream. To simplify leveling of products with different demand levels a related visual scheduling
Visual Control
Visual control is a technique employed in many places where information is communicated by using visual signals instead of texts or other written instructions. The design is deliberate in allowing quick recognition of the information being communicated, in order to increase efficiency and clarity...

 board known as a heijunka box
Heijunka box
A heijunka box is a visual scheduling tool used in heijunka, a concept created by Toyota for achieving a smoother production flow originally. Whilst heijunka refers to the concept of achieving production smoothing, the heijunka box is the name of a specific tool used in achieving the aims of...

 is often used in achieving these heijunka style efficiencies. Other production leveling techniques based on this thinking have also been developed. Once leveling by product is achieved then there is one more leveling phase, that of "Just in Sequence
Just in Sequence
Just in Sequence is an inventory strategy that matches Just In Time and complete fit in sequence with variation of assembly line production. Components and parts arrive at a production line right in time as scheduled before they get assembled. Feedback from the manufacturing line is used to...

" where leveling occurs at the lowest level of product production.

The use of production leveling as well as broader lean production techniques helped Toyota
Toyota Production System
The Toyota Production System is an integrated socio-technical system, developed by Toyota, that comprises its management philosophy and practices. The TPS organizes manufacturing and logistics for the automobile manufacturer, including interaction with suppliers and customers...

 massively reduce vehicle production times as well as inventory levels during the 1980s.

Implementation

Even Toyota have not yet moved to the final stage in this journey for all their processes which is single-piece flow; indeed they recommend following their journey rather than trying to jump into an intermediate stage. The reason Toyota advocate this is that each production stage is accompanied by adjustments and adaptations to support services to production; if those services are not given these adaptation steps then major issues can arise.
  1. Implement Green stream/Red stream or Fixed sequence, fixed volume to establish the entry and exit criteria for products from these streams and establish the supporting disciplines in the support services. The cycle established will produce Every Product Every Cycle (EPEC). This is a specific form of Fixed Repeating Schedule
    Fixed Repeating Schedule
    Fixed Repeating Schedule is a key element of the Toyota Production System and Lean Manufacturing. As its name suggests it is a production schedule which is 'unchanging' and repeated perhaps daily or over a longer period such as a two weeks or month...

    . Green stream products are those with predictable demand, Red stream products are high value unpredictable demand products.
  2. Faster fixed sequence with fixed volume keep the streams the same but use the now established familiarity with the streams to maximise learning and improve speed of production (economies of repetition). This will allow the shortening of the EPEC cycle so that the plant is now producing every product every 2 weeks instead of month and then later on repeating every week. This may require support services to speed up as well.
  3. Fixed sequence with unfixed volume keep the stream sequences the same but now phase in allowing actual sales to influence volumes within those sequences. This affects inbound componentry as well as support services. This is a more generalised form of Fixed Repeating Schedule
    Fixed Repeating Schedule
    Fixed Repeating Schedule is a key element of the Toyota Production System and Lean Manufacturing. As its name suggests it is a production schedule which is 'unchanging' and repeated perhaps daily or over a longer period such as a two weeks or month...

    .
  4. Unfixed sequence with fixed volume the stream sequences, and EPEC, can now be gradually flexed but move to small fixed batch sizes to make this more manageable.
  5. Unfixed sequence with unfixed volume finally move to true single piece flow and pull by reducing batch sizes until they reach one.

Demand leveling

Demand leveling is the deliberate influencing of demand itself or the demand processes to deliver a more predictable pattern of customer demand. Some of this influencing is by manipulating the product offering, some by influencing the ordering process and some by revealing the demand amplification induced variability of ordering patterns. Demand levelling does not include influencing activities designed to clear existing stock.

History

Demand management has been approached in a variety of ways:

For one method of demand management it is instructive to look at Toyota in its home market, Japan. Toyota sales teams sell cars door-to-door whereby they build customer profiles and relationships. The sales process is low intensity but includes test drives, financing, insurance and trade-in deals. The sale itself is by special order placed with their representative. This means that orders can be predicted reasonably accurately in terms of vehicle numbers some way in advance. Finer specific vehicle details may only become known with the order. However, the order is often for delivery in the future so these details can usually be planned before build.

Because the customer is getting the exact car they want there is less negotiation around price as indeed the fact that the build is to order removes the incentive of the manufacturer, or their agent, to discount existing stock. The aim of this system is to maximise the revenue from the customer in the long term. This leads to the sales team handling after-sales issues of diverse kinds for an extended period to keep customer loyalty and the relationship which will sell the next car. Between purchases the sales team remain in touch for all aspects of customer satisfaction with their cars including feedback for product design on changing customer preferences in the market.

The Japanese market does not have the seasonal, promotional or other demand surges that are a characteristic of Western automotive markets. It is debated, for both markets, whether this is caused by manufacturers' behaviour or whether manufacturers' behaviour is a logical response to it.

A second approach to demand management is by deep understanding of the systems used to order products by retailers and other sellers from manufacturers. Even where this supply chain
Supply chain
A supply chain is a system of organizations, people, technology, activities, information and resources involved in moving a product or service from supplier to customer. Supply chain activities transform natural resources, raw materials and components into a finished product that is delivered to...

 is very simple, customer-retailer-manufacturer, it is usually the case that orders are based on some form of Economic Order Quantity
Economic order quantity
Economic order quantity is the level of inventory that minimizes total inventory holding costs and ordering costs. It is one of the oldest classical production scheduling models. The framework used to determine this order quantity is also known as Wilson EOQ Model or Wilson Formula. The model was...

 (EOQ) calculation that aggregates actual customer demand over a certain period. This aggregation, and the other clever calculations that may be involved, often obscure the fact that actual demand for a product is close to flat, and for high volume products very close to flat. The demand pulsing effect is created by the ordering process and the more complex it is the greater this effect. The use of EPOS
Point of sale
Point of sale or checkout is the location where a transaction occurs...

 actual sales data can reveal this effect very clearly.

A third approach to demand management is the keeping of Finished Goods (FG) or nearly Finished Goods stock to acts to isolate the production facility from actual demand. This approach is widely used today but its weakness is becoming more and more evident as a growing variety of products is demanded. The cost of making, storing, managing and protecting FG stock can grow to be prohibitive depending upon product range and demand variability levels. This usually means that actually whilst stocks are kept they are insufficient to meet the stated aims and so customer dissatisfaction ensues along with distressed sales (reduced price) to eliminate stock levels seen as too high.

Implementation

If it is accepted that a large part of demand variability in high volume products can be substantially caused by sales and ordering process artifacts then analysis and leveling can be attempted.

The use of long delay supply chain
Supply chain
A supply chain is a system of organizations, people, technology, activities, information and resources involved in moving a product or service from supplier to customer. Supply chain activities transform natural resources, raw materials and components into a finished product that is delivered to...

s to reduce manufacturing costs often means that production orders are placed long before customer demand can be realistically estimated. The much later arrival of forecast product demand volumes makes demand leveling irrelevant since the issue has now switched to disposal at best price possible products that are already created and possibly paid for. Demand leveling has only proven possible where build times have been made relatively low and production has been made relatively reliable and flexible. Examples of these are fast airborne supply chains (e.g. Apple iPod) or direct to customer selling through web sites allowing late customisation (e.g. NIKEiD custom shoes) or local manufacture (e.g. Timbuk2 custom courier bags).

Where actual build-delivery times can be brought within the same scale as customer time horizons then effort to modify impulse buying and make it somewhat planned can be successful. Reliable, flexible manufacturing will then mean that low stock levels (if any) do not interfere with customer satisfaction and that incentives to sell what has been produced eliminated.

Where demand follows a predictable pattern, e.g. flat, then regular deliveries of constant amounts can be agreed with variances in actual demand ignored unless it exceeds some agreed trigger level. Where this cannot be agreed then it can be simulated and the benefits gained through frequent deliveries
Frequent deliveries
Frequent deliveries are a largely ignored but powerful way of leveling apparent demand within a supply chain and thereby reducing Mura. What is perhaps not so obvious is that this will reduce inventory levels and thereby assist progress along the Lean journey at the same time...

 and a market location
Manufacturing supermarket
A manufacturing supermarket is, for a factory process, what a retail supermarket is for the customer. The customers draw products from the 'shelves' as needed and this can be detected by the supplier who then initiates a replenishment of that item...

.

The predictable pattern does not have to be flat and may, for example, be an annual pattern with higher volumes at particular periods. Here again the deliveries can be agreed to follow a simplified but similar pattern, perhaps one delivery volume for six months of the year and another for the other six months.
The source of this article is wikipedia, the free encyclopedia.  The text of this article is licensed under the GFDL.
 
x
OK