Burn rate
Encyclopedia
Burn rate is a synonymous term for negative cash flow
Cash flow
Cash flow is the movement of money into or out of a business, project, or financial product. It is usually measured during a specified, finite period of time. Measurement of cash flow can be used for calculating other parameters that give information on a company's value and situation.Cash flow...

. It is a measure for how fast a company will use up its shareholder capital. If the shareholder capital is exhausted, the company will either have to start making a profit, find additional funding, or close down.

The term came into common use during the dot-com era when many start-up companies went through several stages of funding before emerging into profitability and positive cash flows and thus becoming self-sustainable (or, as for the majority, failing to find additional funding and sustainable business models and thus going bankrupt). In between funding events, burn rate becomes an important management measure, since together with the available funds, it provides a time measure to when the next funding event needs to take place.

Some claim that part of the reasons behind the dot-com bust was the unsound management and financial investor practices to keep the burn rate up, taking it as a proxy for how fast the start-up company was acquiring a customer base.

The term burn rate can also refer to how quickly individuals spend their money, particularly their discretionary income. For example, Mackenzie Investments commissioned a test to gauge the spending and saving behavior of Canadians to determine if they are “Overspenders.”

Burn rate in project management

Aside from financing, the term burn rate is also used in project management
Project management
Project management is the discipline of planning, organizing, securing, and managing resources to achieve specific goals. A project is a temporary endeavor with a defined beginning and end , undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value...

 to determine the rate at which hours (allocated to a project) are being used, to identify when work is going out of scope, or when efficiencies are being lost. Simply put, the burn rate of any project is the rate at which the project budget is being burned (spent).

In earned value management
Earned value management
Earned value management is a project management technique for measuring project performance and progress in an objective manner. EVM has the ability to combine measurements of scope, schedule, and cost in a single integrated system. Earned Value Management is notable for its ability to provide...

, burn rate is calculated via the formula, 1/CPI, where CPI stands for Cost Performance Index, which is equal to Earned Value / Actual Cost.

External links

The source of this article is wikipedia, the free encyclopedia.  The text of this article is licensed under the GFDL.
 
x
OK