Assumption based planning
Encyclopedia
Assumption-based planning in project management
is a post-planning method that helps companies to deal with uncertainty. It is used to identify the most important assumptions in a company’s business plan
s, to test these assumptions, and to accommodate unexpected outcomes.
A solution to this problem is to make assumptions and attempt to predict future outcomes. Some of the assumptions made during the planning process are very likely to come true; the outcome of others is very much uncertain, though not unimportant. Assumption-based planning identifies and tests the assumptions made in a business plan, the formulation of “hedging actions” and the construction of “what-if” scenarios.
Uncertainties are identified and plans can be prepared for what to do if original predictions prove to be false. Assumption-based planning does not demand accuracy for all assumptions made in a business plan, but builds a reasonable model to assess the assumptions involved.
Assumption-based planning methods include:
Assumption-based planning methodologies provided the foundation for other planning frameworks and tools such as Robust decision making
.
The identification of assumptions may lead to a change in the business plan, so advocates of assumption-based planning argue that it should be at the core of business planning.
defines an assumption as “an assertion about some characteristic of the future that underlies the current operations or plans of an organization.” There are several types of assumption. Include implicit and explicit assumptions, and primary and secondary assumptions, an important aspect of Critical assumption planning
. The two classifications are not mutually exclusive; an assumption can be both explicit and primary.
Project management
Project management is the discipline of planning, organizing, securing, and managing resources to achieve specific goals. A project is a temporary endeavor with a defined beginning and end , undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value...
is a post-planning method that helps companies to deal with uncertainty. It is used to identify the most important assumptions in a company’s business plan
Business plan
A business plan is a formal statement of a set of business goals, the reasons why they are believed attainable, and the plan for reaching those goals. It may also contain background information about the organization or team attempting to reach those goals....
s, to test these assumptions, and to accommodate unexpected outcomes.
Overview
Conventional business planning works on the expectation that managers can extrapolate future results from past experience, but for new businesses and projects this way of planning is often not possible. Experience may be lacking or extrapolating from past experience may be misleading.A solution to this problem is to make assumptions and attempt to predict future outcomes. Some of the assumptions made during the planning process are very likely to come true; the outcome of others is very much uncertain, though not unimportant. Assumption-based planning identifies and tests the assumptions made in a business plan, the formulation of “hedging actions” and the construction of “what-if” scenarios.
Uncertainties are identified and plans can be prepared for what to do if original predictions prove to be false. Assumption-based planning does not demand accuracy for all assumptions made in a business plan, but builds a reasonable model to assess the assumptions involved.
Assumption-based planning methods include:
- Critical assumption planningCritical assumption planningCritical assumption planning is a service mark of D. Dunham & Co and was described in Journal of Business Venturing by Sykes in 1995. Critical Assumption Planning helps managers and entrepreneurs maximize business development learning at least cost...
(CAP) by D. Dunham & Co. - Assumption-based planning by RANDRANDRAND Corporation is a nonprofit global policy think tank first formed to offer research and analysis to the United States armed forces by Douglas Aircraft Company. It is currently financed by the U.S. government and private endowment, corporations including the healthcare industry, universities...
: raises the visibility of make-or-break uncertainties common to new ventures by forcing managers to admit what they don’t know. - Discovery-Driven Planning by Rita Gunther McGrathRita Gunther McGrathRita Gunther McGrath is an Associate Professor of Management at the Columbia University Graduate School of Business . She joined Columbia in 1993 after completing her Ph.D. at The Wharton School of the University of Pennsylvania...
and Ian C. MacMillan.
Assumption-based planning methodologies provided the foundation for other planning frameworks and tools such as Robust decision making
Robust decision making
Robust decision making is an iterative decision analytic framework that helps identify potential robust strategies, characterize the vulnerabilities of such strategies, and evaluate the tradeoffs among them...
.
Position in business planning process
Most business planning methods or books about “how to write a business plan” indicate that you should write down your financial assumptions at the end of your plan, but assumption-based planning encourages managers to actively plan and monitor the validation of these assumptions.The identification of assumptions may lead to a change in the business plan, so advocates of assumption-based planning argue that it should be at the core of business planning.
Types of assumption
RANDRAND
RAND Corporation is a nonprofit global policy think tank first formed to offer research and analysis to the United States armed forces by Douglas Aircraft Company. It is currently financed by the U.S. government and private endowment, corporations including the healthcare industry, universities...
defines an assumption as “an assertion about some characteristic of the future that underlies the current operations or plans of an organization.” There are several types of assumption. Include implicit and explicit assumptions, and primary and secondary assumptions, an important aspect of Critical assumption planning
Critical assumption planning
Critical assumption planning is a service mark of D. Dunham & Co and was described in Journal of Business Venturing by Sykes in 1995. Critical Assumption Planning helps managers and entrepreneurs maximize business development learning at least cost...
. The two classifications are not mutually exclusive; an assumption can be both explicit and primary.
Implicit and explicit assumptions
Explicit assumptions are assumptions of which the intention that is fully revealed or expressed without vagueness, implication or ambiguity. However, explicit statements in a plan often have hidden implicit assumptions. Implicit assumptions are assumptions that are not expressed and may go undetected. If implicit assumptions prove to be wrong, this can damage projects.
|
Process of assumption-based planning
The steps of assumption-based planning are:- Identify assumptions: Collect all assumptions implicit, explicit, primary and derivative, out of the (business) plan.
- Determine criticality: Try to quantify the assumptions as much as possible in order to determine which assumptions have the greatest (financial) impact.
- Design tests: Design a test for every critical assumption. In a test design you state how to test the assumption and what proves the assumption wrong or right.
- Schedule tests: Every critical assumption needs to be tested, but not all assumptions can be tested in the present. So future assumptions tests are scheduled in a test schedule. Some possible reasons to schedule a test in the future are a lack of information in the present or a dependency on the test outcomes of other tests.
- Test assumptions: Then an assumption is tested this results in a test outcome, which proves the assumption right or wrong.
- Reassess plan: Based on the test outcomes and the test schedule one might decide to reassess the venture plan and update the business plan with the new insights gathered in the ABP process.
- Plan re-testing: The assumptions need to be re-tested regularly if not constantly. There should be a retest schedule of every critical assumption.
- Create or update the assumption plan: The assumption plan holds all data gathered during the ABP process.